Construction Progress

Sterling Quadrangle

Upcoming Updates

Nov 2026
Leasing Office Acceptance

  • The leasing office and lobby are scheduled for final completion and acceptance.

  • Fitness and yoga room furnishings, equipment and specialty finishes will be installed.

  • Landscaping, sidewalks and exterior improvements around Buildings 1 and 2 are scheduled for completion.

  • Pergolas, hardscape, plantings and outdoor features will continue in the residential courtyards.

  • The first parking garage elevator is scheduled to complete final finishes and testing.

Sterling Quadrangle construction progress photo
Sterling Quadrangle construction progress photo
Sterling Quadrangle rendering of the covered exterior patio

    Dec 2026
    Fitness Spaces Complete

    • The fitness and yoga spaces are scheduled for completion.

    • The parking garage freight elevator is scheduled for completion.

    • Courtyard improvements for Buildings 2 and 3—including landscaping, hardscape and outdoor gathering areas—are scheduled for completion.

    • The covered exterior patio is expected to receive its furniture, millwork, tile and wall finishes.

    • The first groups of apartment homes will begin reaching final inspection and punch-list stages.

    Sterling Quadrangle construction progress photo
    Sterling Quadrangle construction progress photo
    Sterling Quadrangle rendering of the covered exterior patio

      Jan 2027
      Amenities Operational

      • The leasing and amenity areas are scheduled to reach their first operational milestone.

      • The first residential elevator is scheduled for completion.

      • Flooring, appliances, plumbing fixtures, mirrors, blinds and final finishes will continue throughout the apartment homes.

      • Completed areas will begin moving through inspections, cleaning and quality-control walks.

      Sterling Quadrangle construction progress photo
      Sterling Quadrangle construction progress photo
      Sterling Quadrangle rendering of the covered exterior patio

        Feb 2027
        Pool Commissioning

        • The second residential elevator is scheduled for completion.

        • Pool equipment will be connected, followed by plastering, filling and balancing the pool.

        • Pool inspections, glass installation and shower finishes are scheduled.

        • Additional apartment homes will move through final inspections and punch-list work.

        Sterling Quadrangle construction progress photo
        Sterling Quadrangle construction progress photo
        Sterling Quadrangle rendering of the covered exterior patio

          Looking Ahead

          March 2027

          • Building 1 is scheduled to reach its operational milestone.

          • The pool and courtyard are scheduled for completion by March 15.

          • Parking garage painting, striping, signage and final inspections are scheduled for completion.

          April 2027

          • Building 2B is scheduled to reach its operational milestone.

          • Parking garage finishes and owner acceptance are scheduled for completion by April 21.

          • Leasing and amenity construction is scheduled to conclude by April 22.

          May 2027

          • Building 3 is scheduled to reach its operational milestone.

          • Final corrections, inspections and quality-control work will continue throughout the community.

          June 2027

          • Buildings 2C and 2A are scheduled to reach their operational milestone.

          • Final cleaning, owner acceptance and closeout activities will continue.

          July – September 2027

          • Remaining contingency work, corrections and final project closeout will occur in phases.

          • Building 1’s construction duration is scheduled to conclude in July.

          • Building 2B’s construction duration is scheduled to conclude in August.

          • Building 3 is scheduled to conclude in early September.

          • Buildings 2C and 2A—and the overall project schedule—are currently shown concluding by September 22, 2027.

          August 2027

          • Crews will focus on remaining touchups, corrections and final details throughout the community.

          • Building 3’s overall construction work is scheduled to conclude.

          • Sterling Tiger Valley is expected to reach substantial completion in August.

          • Final closeout work will continue as the community prepares for residents.