Construction Progress
Sterling Quadrangle
Upcoming Updates
- Nov 2026
Leasing Office Acceptance - Dec 2026
Fitness Spaces Complete - Jan 2027
Amenities Operational - Feb 2027
Pool Commissioning
Nov 2026
Leasing Office Acceptance
-
The leasing office and lobby are scheduled for final completion and acceptance.
-
Fitness and yoga room furnishings, equipment and specialty finishes will be installed.
-
Landscaping, sidewalks and exterior improvements around Buildings 1 and 2 are scheduled for completion.
-
Pergolas, hardscape, plantings and outdoor features will continue in the residential courtyards.
-
The first parking garage elevator is scheduled to complete final finishes and testing.
Dec 2026
Fitness Spaces Complete
-
The fitness and yoga spaces are scheduled for completion.
-
The parking garage freight elevator is scheduled for completion.
-
Courtyard improvements for Buildings 2 and 3—including landscaping, hardscape and outdoor gathering areas—are scheduled for completion.
-
The covered exterior patio is expected to receive its furniture, millwork, tile and wall finishes.
-
The first groups of apartment homes will begin reaching final inspection and punch-list stages.
Jan 2027
Amenities Operational
-
The leasing and amenity areas are scheduled to reach their first operational milestone.
-
The first residential elevator is scheduled for completion.
-
Flooring, appliances, plumbing fixtures, mirrors, blinds and final finishes will continue throughout the apartment homes.
-
Completed areas will begin moving through inspections, cleaning and quality-control walks.
Feb 2027
Pool Commissioning
-
The second residential elevator is scheduled for completion.
-
Pool equipment will be connected, followed by plastering, filling and balancing the pool.
-
Pool inspections, glass installation and shower finishes are scheduled.
-
Additional apartment homes will move through final inspections and punch-list work.
Looking Ahead
March 2027
-
Building 1 is scheduled to reach its operational milestone.
-
The pool and courtyard are scheduled for completion by March 15.
-
Parking garage painting, striping, signage and final inspections are scheduled for completion.
April 2027
-
Building 2B is scheduled to reach its operational milestone.
-
Parking garage finishes and owner acceptance are scheduled for completion by April 21.
-
Leasing and amenity construction is scheduled to conclude by April 22.
May 2027
-
Building 3 is scheduled to reach its operational milestone.
-
Final corrections, inspections and quality-control work will continue throughout the community.
June 2027
-
Buildings 2C and 2A are scheduled to reach their operational milestone.
-
Final cleaning, owner acceptance and closeout activities will continue.
July – September 2027
-
Remaining contingency work, corrections and final project closeout will occur in phases.
-
Building 1’s construction duration is scheduled to conclude in July.
-
Building 2B’s construction duration is scheduled to conclude in August.
-
Building 3 is scheduled to conclude in early September.
-
Buildings 2C and 2A—and the overall project schedule—are currently shown concluding by September 22, 2027.
August 2027
-
Crews will focus on remaining touchups, corrections and final details throughout the community.
-
Building 3’s overall construction work is scheduled to conclude.
-
Sterling Tiger Valley is expected to reach substantial completion in August.
-
Final closeout work will continue as the community prepares for residents.