Construction Progress
Sterling Quadrangle
Sep 2026
Exteriors & Interiors
Oct 2026
Amenities & Site Work
Nov 2026
Finishing Touches
Dec 2026
Final Inspections
Sep 2026
Exteriors & Interiors
Roofing and exterior façade work are nearing completion across the residential buildings.
Parking garage utility and life-safety rough-ins are being completed.
Electrical meters are being released and installed.
Interior finishes are progressing throughout the residential buildings.
Leasing office, lobby, fitness and yoga room buildouts are underway.
Pool courtyard grading, utilities, irrigation and foundation work have begun.
Oct 2026
Amenities & Site Work
Flooring, millwork, countertops, wall finishes and furnishings are being installed in the leasing office and lobby.
Finishes are progressing in the fitness and yoga spaces.
Pool courtyard hardscape, pergola, outdoor kitchen, fire pit and landscaping installations are scheduled.
Sidewalk, irrigation and landscaping work will continue around the residential buildings.
The first parking garage elevator is scheduled to be installed.
Apartment interiors will continue progressing with paint, trim, cabinetry, countertops and flooring.
Nov 2026
Finishing Touches
The leasing office and lobby are scheduled for final completion and acceptance.
Fitness and yoga room furnishings, equipment and specialty finishes will be installed.
Landscaping, sidewalks and exterior improvements around Buildings 1 and 2 are scheduled for completion.
Pergolas, hardscape, plantings and outdoor features will continue in the residential courtyards.
The first parking garage elevator is scheduled to complete final finishes and testing.
Dec 2026
Final Inspections
The fitness and yoga spaces are scheduled for completion.
The parking garage freight elevator is scheduled for completion.
Courtyard improvements for Buildings 2 and 3—including landscaping, hardscape and outdoor gathering areas—are scheduled for completion.
The covered exterior patio is expected to receive its furniture, millwork, tile and wall finishes.
The first groups of apartment homes will begin reaching final inspection and punch-list stages.